Repairs will start to the road on Monday June 16th 2014

Roads will be closed to all traffic whilst stage one of the repairs are carried out as follows:

Monday16th June 8am to 5pm approximately

Planing of Lime Tree walk

Residents of Lime Tree Walk will need to locate their cars in either of the overflow car parks and park on the road running from Connolly Court to the front entrance of Crossland House.

Tuesday 17th June 2014 8am to 5pmLime Tree walk reinstatement of road surface in preparation for the resin bonding which will take place in approximately 5 weeks.

Planing Chapel Square outside of No 16 and No 32

Planing the area to the front of the archway entrance to Connolly Court.

All traffic during this time will be directed down the main drive Upper Walk

Wednesday 18th June 2014

Reinstatement of Chapel square and Connolly court in preparation for the resin bond as above

Thursday 19th – 24th June 2014

Fine milling of upper walk

Residents of Upper Walk will need to locate their cars in either of the overflow car parks or park on the road running from Connolly Court to the front entrance of Crossland House.

Traffic management will be in place in order to keep traffic moving but would ask all resident to co-operate with instructions given to then by both Estate staff and contractor.

Failure to re-park your car in the designated areas prior to 8am may result in you being unable to move your vehicle for several hours.

Thank you for your understanding and co-operation in this important work. We apologise for any inconvenience caused.